Arnold Construction

Soil Nail Walls

What is a soil nail wall?

A soil nail wall is a a “top-down” retaining wall constructed in 5′ lifts by drilling rows of nails and applying a shotcrete face.  The nails start at the existing ground surface and are installed as the ground in front of the wall is excavated in lifts.  The purpose is to construct a retaining wall (temporary or permanent) where sloping per OSHA is not possible due to existing structures, utilities, or property lines.

The first soil nail wall was constructed in 1972 near Versailles, France to stabilize a 60′ deep excavation for a railroad widening project.  Prior to soil nails, most excavations were stabilized with driven sheet piles or H-piles with wood lagging that were either anchored or internally braced.

Temporary or Permanent Wall

 

Advantages

  • Soil nail walls are installed more quickly and cost effectively than other shoring systems.
  • Soil nails are an excellent alternative when soil overlies hard material or rock.
  • A wide variety of facings can be used..  Permanent walls can have a finished shotcrete face or any veneer such as brick, stone, or modular blocks.
  • The nails can be drilled and grouted or driven members.
  • Soil nails work well in the piedmont residual soils found in our region of Virginia, North Carolina, South Carolina, Tennessee and Georgia. Read more about the advantages of soil nails          

Limitations

  • For construction, the soil must stand in 5′ lifts during construction.  Therefore, soil nails walls are not typically used in clean sands such as might be found in coastal plain geology.
  • Since the nails are installed on a typical 5′ x 5′ pattern, it is not a good solution where multiple utility conflicts may be encountered in the zone of nails.

Construction

Contractors drill nails on a close pattern and applying the shotcrete facing in lifts.   A 5′ lift is excavated.  A row of nails are then installed on that lift.  Steel reinforcement such as WWF and rebar are then placed at and shotcrete is applied.  That lift is now complete and the site is excavated an additional 5′ and the process is repeated.

Nails are typically drilled on a 5′ x 5′ pattern.  The length of the nails are typically 100% to 125% of the wall height.  The nails may decrease in length near the bottom of the wall. The nails are installed by drilling 4″ to 6″ diameter holes into which a threaded rod is inserted.  The hole is then grouted to attach the threaded rod to the ground.

  • Excavate 5′
  • Drill 4″ to 6″ diameter holes and grout in place an all thread bar
  • Place reinforcement and shotcrete
  • Proof test 5% of the nails
  • Repeat process to the bottom of the excavation
Design

Contractors typically design walls using a limit equilibrium analysis.  Think of the sliding block experiment in high school physics lab where you may have calculated what force is required to overcome friction and move a sandpaper block along an incline.  As a wedge of soil (see the curved plane in the diagram above) tries to slide into the excavation, the wedge of soil is retained by the soil nails and the friction of the ground moving against itself.  The nails get their capacity from the friction between the grouted nail hole and the ground.  The walls are designed to have a factor of safety of 1.35 to 1.5, meaning 35% to 50% more resisting force than is required to stabilize the wall.  Since some movement is required for the soil to develop sliding friction against itself and for the nails to engage in friction, soil nail walls typically move 0.1% to 0.4% of the wall height; 1/4″ to 1″ on a 20′ wall.

Learn more about soil nail wall design

Learn simple QC measures for a successful wall

Other Resources

FHWA Soil Nail Manual
DFI Anchored Earth Retention Committee
Guidance for Design of Temporary Soil Nail Walls, DFI and ADSC

Photos

Testimonials

ERIC PERKINSON, BRASFIELD & GORRIE

When we need a soil nail wall sub again, I highly recommend Subsurface. They worked with our ever changing schedule without complaining.

CHARLIE MCINTOSH, ENVIRONMENT QUALITY RESOURCES

Due to the location of the project, North Carolina State University, I was very impressedat the crews manners and respect for their surroun dings. They acted very professionally.

JOHN MADDUX, FAULCONER CONSTRUCTION

Subsurface has always been good to work with and this project was no exception! look forward to working with you guys in the future.

DWAYNE RAKESTRAW, NEW ATLANTIC CONTRACTING

We wish all subcontractors were as professional and cooperative as your team.

PHILLIP MEADORS, BEK

Subsurface was enjoyable to work with on a daily basis on a project which had many moving parts and difficult interaction between trades. Very responsive and made effort to be effective in completing the required scope of work.

ANDREW HAGOOD, BALFOUR BEATTY

The Subsurface Construction team exceeded our expectations in every phase of the project. When challenges presented themselves, the field and office teams were proactive in overcoming them and stayed on schedule. From the bottom to the top, they are driven..

PATRICK RICCI, BALFOUR BEATTY CONSTRUCTION

The field Teams did all they could to expedite and work as hard as possible. Robert, Chuck, and Jeff all worked well with myself and BBC field team. I am pleased to have had the opportunity to meet and work..

MICHAEL CHRISTIE, RALEIGH DURHAM ROAD BUILDERS

Due to our tight schedule we needed Subsurface to expedite design. Subsurface came through for us and we met the schedule and satisfied our challenging owner.

JOE STOYKO, BE&K

Subsurface was very well organized and their Salety program went beyond expectations. Great job!

PRENTICE UZZELL, PE, RN ROUSE

An excellent member of our team... RN Rouse and the owner were vey pleased with their efforts in nmaking the beginning phases of this project a success.