Anchored soldier pile walls are offered as a solution when the site requires a stiff excavation shoring system, especially with multiple utility conflicts.
A soldier pile wall is a a “top-down” retaining wall consisting of vertical steel piles, wood lagging, and anchors as required. The purpose is to construct a retaining wall (temporary or permanent) where sloping per OSHA is not possible due to existing structures, utilities, or property lines. Soldier piles are the most common shoring system used for excavations in dense downtown areas.
Soldier piles were the original excavation shoring system. In the past, this system was commonly referred to as a Berlin Wall owing to its use in Europe more than a century ago. These walls were braced internally to retain the earth. Anchors were developed for a dam in Africa in the 1930’s. Anchors were later used with soldier pile walls to eliminate internal bracing.
Contractors drive or drill and set piles depending on ground conditions, vibration restrictions, and noise limits. Piles are typically installed on an 6′ to 10′ horizontal spacing. Wood lagging is installed in two 5′ lifts to a depth of 10′. At this point, anchors would be drilled and prestressed for the load required for the full height of the excavation. Wood lagging would then continue in 5′ lifts to the bottom of the excavation.
Contractors typically design soldier pile walls using a limit equilibrium analysis. Think of the sliding block experiment in high school physics lab where you calculated the force required to overcome friction and move a sandpaper block along an incline. As a wedge of soil tries to slide into the excavation, the wedge of soil is retained by the steel piles, anchor force, and the friction of the ground moving against itself. The piles provide resistance by pushing against the soil in front of the wall below the excavation. The anchors get their capacity from the friction between the grouted anchor and the ground. The walls are designed to have a factor of safety of 1.35 to 1.5, meaning 35% to 50% more resisting force than is required to stabilize the wall. Since the anchors are prestressed, wall movement is limited.
FHWA Ground Anchors and Anchored Systems
DFI Anchored Earth Retention Committee
Due to the location of the project, North Carolina State University, I was very impressedat the crews manners and respect for their surroun dings. They acted very professionally.
Subsurface has always been good to work with and this project was no exception! look forward to working with you guys in the future.
We wish all subcontractors were as professional and cooperative as your team.
Subsurface was enjoyable to work with on a daily basis on a project which had many moving parts and difficult interaction between trades. Very responsive and made effort to be effective in completing the required scope of work.
The Subsurface Construction team exceeded our expectations in every phase of the project. When challenges presented themselves, the field and office teams were proactive in overcoming them and stayed on schedule. From the bottom to the top, they are driven..
The field Teams did all they could to expedite and work as hard as possible. Robert, Chuck, and Jeff all worked well with myself and BBC field team. I am pleased to have had the opportunity to meet and work..
Due to our tight schedule we needed Subsurface to expedite design. Subsurface came through for us and we met the schedule and satisfied our challenging owner.
Subsurface was very well organized and their Salety program went beyond expectations. Great job!
An excellent member of our team... RN Rouse and the owner were vey pleased with their efforts in nmaking the beginning phases of this project a success.
When we need a soil nail wall sub again, I highly recommend Subsurface. They worked with our ever changing schedule without complaining.